How to estimate concrete and aggregate demand from a subdivision plat

New homes under construction in a subdivision, framed with scaffolding, beside a freshly paved street and curb with stacked building materials.

A recorded plat is really a takeoff sheet if you know where to look. Most reps either eyeball the lot count and guess, or they wait for the civil set to land on their desk, which can be sixty days after the plat recorded. There's a middle path: you can get a workable yardage estimate straight off the plat itself, before a single engineer has drawn a street cross-section for you.

What's actually on the page

A final plat gives you four things you can take to the bank: lot count, lot dimensions, linear footage of new street frontage, and the right-of-way width. Sometimes you also get a note calling out the pavement section if the county required it on the face of the plat, though more often that lives in the construction plans instead.

Start with the lot table. Count detached single-family lots separately from townhome lots and any multi-family or commercial pads, because they don't scale the same way. A 60-foot-wide lot with a detached slab-on-grade house pulls a very different concrete number than an 18-foot townhome lot sharing party walls.

Next, measure street centerline off the plat's dimension lines or scale it against the plat's bar scale if dimensions aren't called out on every segment. Add up linear footage for every new public street, plus any private drive or alley shown. That number drives your base stone and your curb-and-gutter quantity, which usually runs by linear foot of curb rather than by lot.

Converting lot count to yardage

Once you have lot count and street footage, the conversion is mostly multiplication using whatever standard sections your market runs.

None of this needs to be precise to the yard. What you're building is a swag good enough to size a bid, flag the account for your inside sales desk, and figure out whether this job needs a second truck route or can ride along an existing one.

Where the estimate actually gets used

The estimate only pays off if you're watching the right parcel at the right time. A lot of reps build this whole takeoff off a plat and then sit on it for eight months because nothing on the ground tells them the developer has actually moved. The plat recording itself isn't the signal. Grading contractors mobilizing, fencing going up, and an access cut appearing where the entrance road will tie in, that's the signal that the site is committed and concrete is coming in a predictable window, usually well before the grading permit shows up in the county's online system. If you'd rather not check the parcel yourself every week, a weekly feed built around exactly that gap flags clearing and access changes on parcels you're watching, so the takeoff you already did isn't sitting in a folder when the trucks could've been booked.

Run the numbers off the plat now, so the only thing you're waiting on later is the ground to move.